The package comes back with one line against it. “Method statement not specific to the proposed system. Resubmit.” Nine sections, the right sequence of work, the right PPE list, returned inside a day. The reviewer wanted a number he could check, and the jointing clause said “fuse as per manufacturer’s recommendation”.
A PP-R installation method statement passes review on one test: every figure in it is traceable to a named source, and every figure carries the condition under which it holds. In practice that means four things. Your jointing clause states the heating, change-over and cooling times with the technical rule and its edition. Your materials clause states the pressure class with its SDR and its wall thickness. The supports clause gives spacing at the design water temperature, not by diameter alone. And the testing clause names the test pressure, the procedure letter and the acceptance limit, with the standard they come from.
Below is that skeleton, with the three PP-R-specific sections filled in from DVS 2207-11:2020-05, EN 806-4:2010 and three makers’ published charts.
Key Takeaways
- Fusion times come from DVS 2207-11:2020-05, at a heated-tool temperature of 260 ±10 °C and 20 °C ambient with moderate air movement. Write both conditions in.
- The rule separates holding from loading: at d 63 that is 30 s held fixed and 6 min total cooling.
- EN 806-4:2010 section 6 sets a test pressure of 1.1 × the maximum allowable operating pressure, a minimum of 11 bar on a 10 bar system, with a 30 minute main test.
- PP-R is viscoelastic, so under EN 806-4 section 6 it takes procedure B or C at every diameter and never procedure A; procedure C allows a fall of under 0.6 bar over the second 30 minutes and not more than 0.2 bar over the following two hours.
- Support spacing falls with temperature: PN20 plain pipe at d 63 runs 170 cm at 20 °C and 125 cm at 80 °C; vertical runs take × 1.3.
- A passed system test is not weld qualification: DVS 2207-1:2005-09, the PE-HD companion code, records that evaluating a socket weld by internal pressure creep test “is only insufficiently possible”, and the PP part states no equivalent.
- The inspection and test plan is a separate submittal. Do not fold hold points and sign-off records into the method statement.

What a PP-R Method Statement Approves, and What the Other Submittal Covers
A method statement describes how the work will be carried out and controlled, in enough detail that a second crew could repeat it. The reviewer signs it to accept a method, which is why a clause deferring to an unnamed manufacturer’s recommendation fails, and why a document covering HDPE, uPVC, copper and PP-R in one pass comes back: neither states 260 ±10 °C, a change-over in seconds or a spacing in centimetres.
The inspection and test plan is the other document: what gets inspected and tested, at which hold points, by whom, against which record. The two cross-reference each other, but a method statement carrying an ITP matrix reads as though nobody knows which submittal is which.
For a PP-R package the system standard matters more than the pipe standard. ISO 15874 splits into part 1 general, part 2 pipes, part 3 fittings, part 5 fitness for purpose of the system, and part 7 guidance on assessing conformity. There is no part 4. The 2013 editions were confirmed in 2023, so they are what a 2026 submittal cites, and part 5 is the part a method statement leans on.
The Nine Sections a Reviewer Expects, and What Gets Each One Returned
The list below is the conventional shape of a building-services method statement, with the rejection reason that applies to each section on a PP-R package. 3 of the 9 carry almost all the technical risk — materials, jointing and testing — and they are the 3 this page fills in, from DVS 2207-11:2020-05 and EN 806-4:2010. The other 6 a reviewer checks for presence, not for numbers.

| Section | What the clause must state | Verdict: what gets it returned |
|---|---|---|
| 1. Scope and references | Drawing and spec numbers; standards by number, part and year | “As per relevant standards” with no designation |
| 2. Responsibilities | Named roles, and who is qualified to fuse | No welder competence route named |
| 3. Plant, tools and calibration | Fusion machine type per size range; how tool temperature is verified | No calibration or temperature-check method |
| 4. Materials and storage | Class with SDR and wall; arrival checks; UV and handling limits | Class named without SDR or wall thickness |
| 5. Sequence of work | Set-out, penetrations, prefabrication, install order | Sequence that tests after walls close |
| 6. Jointing | Parameter table by diameter, with source, tool temperature and ambient | Unsourced table, or no ambient condition |
| 7. Supports and expansion | Spacing by diameter at the design temperature; fixed and sliding points | Spacing table with no temperature column |
| 8. Testing and flushing | Standard, procedure letter, test pressure, hold time, drop limit | A bar figure with no standard and no procedure |
| 9. Safety and environment | Hot-tool controls, permits, waste, risk-assessment reference | Generic PPE list with no hot-work control |
Read the right-hand column as the review: 8 of the 9 rejection reasons are a missing condition, not a wrong value — a 30 s cooling time with no diameter against it, a PN class with no SDR, a test pressure with no procedure letter.
Materials: What We Check, and What Your Clause Must Cite
Write the materials clause so a reviewer with the specification open can tick it line by line. Name ISO 15874 parts 1, 2, 3 and 5 individually rather than the family, and state the pressure class with the dimension ratio it implies and the wall thickness at each diameter. PN10 is SDR 11, PN16 is SDR 7.4, PN20 is SDR 6 and PN25 is SDR 5, as the pressure-class page works through.
The wall number makes the clause checkable. On our PN20 range, DN20 to DN160, the wall runs 3.4 mm at DN20, 5.4 mm at DN32, 10.5 mm at DN63 and 18.4 mm at DN110. Figures for each class sit in the dimensions and tolerance chart and on the Série PPR Global pages.
The Five Checks We Run, and Where They Belong in the Clause
The clause should commit to verification on arrival, not only to a certificate on file. Five checks run here before a PN20 batch ships, and belong on site too:
- Resin grade verified by source and grade.
- Caliper wall checks sampled across multiple pallets, not just the top layer.
- Outside diameter and wall to ISO 15874 and DIN 8077.
- Pressure and thermal testing to the rated class.
- Printed markings reconciled to the certificate numbers.
Our incoming-inspection guide covers running those five on a delivery; the ISO 15874 and DIN 8077 explainer covers what each specifies.
One line most clauses omit: name the supplier of the fittings as well as the pipe. Weldability for polypropylene is confirmed within a melt index group, and SIMONA’s welding handbook puts that window at MFR (190/5) 0.4 to 1.0 g/10 min — a figure nobody can read off a fitting on site, so naming both suppliers is how the clause handles it.
Jointing: The Fusion Parameter Table the Reviewer Is Looking For
Heated-tool socket welding of polypropylene is governed by DVS 2207-11:2020-05, the current edition of the PP part. The table below reproduces its figures as published in SIMONA’s work.info welding handbook, October 2023, Table 29, for SDR 11 pipe at a heated-tool temperature of 260 ±10 °C, at 20 °C ambient with moderate air movement.

| Outside diameter d (mm) | Heating time (seconds) | Change-over, max (seconds) | Held fixed (seconds) | Total cooling (minutes) |
|---|---|---|---|---|
| 20 | 5 | 4 | 6 | 2 |
| 25 | 7 | 4 | 10 | 2 |
| 32 | 8 | 6 | 10 | 4 |
| 40 | 12 | 6 | 20 | 4 |
| 50 | 18 | 6 | 20 | 4 |
| 63 | 24 | 8 | 30 | 6 |
| 75 | 30 | 8 | 30 | 6 |
| 90 | 40 | 8 | 40 | 6 |
| 110 | 50 | 10 | 50 | 8 |
| 125 | 60 | 10 | 60 | 8 |
The column most documents collapse is the last pair. “Held fixed” is how long the joint must be held without movement; “total cooling” is how long before it may be loaded by further laying. At d 63 that is 30 s of holding and 6 min before the run is touched again — a programme built on the 30 s misreads the rule by a factor of twelve.
Two independent maker charts reproduce this set exactly: FV-Plast’s FV AQUA manual prints the same heating times from 5 s at d 16 to 60 s at d 125 and the same cooling minutes, Peštan’s PPR catalogue the same from d 20 to d 110.
Where they differ is small and worth knowing: Peštan allows 3 s of correction at d 20 and d 25 where DVS caps change-over at 4 s, and sets the tool at 260 °C ±5 °C against the rule’s ±10 °C. Do not split the difference: name one chart as governing and attach it. Our fusion temperature and time chart and the step-by-step fusion sequence cover the bench work.
The Three Conditions That Make Those Times Valid, or Void
Wall thickness is the first. In Table 29 the SDR 17 column is blank from d 16 to d 50, footnoted “not to be recommended because wall thickness is inadequate”; SDR 17 figures appear only from d 63 to d 125 and run well short of the SDR 11 times, 10 s against 24 s at d 63. Plumbing classes sit on the thick side: PN20 is SDR 6, so at DN63 the crew fuses a 10.5 mm wall, not the SDR 11 wall the column was set for.
Ambient temperature is the second, and the condition most often left out. The welding area has to be protected from moisture, wind, strong sunlight and temperatures below +5 °C. That is not a ban on cold-weather work: with prewarming, a tent or applied heat holding the pipe wall at a workable temperature, welding may proceed at any outdoor temperature. Watch the dew point, bring both parts to the same temperature, and make trial welds when in doubt.

Where a maker publishes a low-temperature column, use it: aquatherm’s North America installer manual switches to its cold column at an ambient of 40 °F, 4.4 °C, taking d 20 from 5 s to 8 s, and runs 50 to 60 % longer across the size range.
Pipe construction is the third. Glass-fibre composite PP-R welds by the identical procedure; FV-Plast states plainly that its fibre-reinforced pipes “do not have to be specially modified for the actual welding process”. Aluminium-layer PPR/AL/PPR is a different line, and no public technical rule we could source states its jointing preparation: attach that maker’s own instruction and cite it rather than borrowing the plain PP-R procedure.
Supports and Expansion: Spacing Is a Function of Temperature
A supports table with one spacing per diameter is the clause a consultant on a hot-water package will stop at. Polypropylene softens as it warms, so the span a clip carries falls with the medium temperature. The figures below are FV-Plast’s maximum support distances for PN20 plain PP-R on horizontal runs, Table 18c.

| Outside diameter d (mm) | At 20 °C (cm) | At 40 °C (cm) | At 60 °C (cm) | At 80 °C (cm) |
|---|---|---|---|---|
| 20 | 95 | 85 | 80 | 70 |
| 25 | 100 | 100 | 90 | 85 |
| 32 | 120 | 115 | 100 | 90 |
| 40 | 130 | 125 | 115 | 100 |
| 50 | 150 | 140 | 125 | 110 |
| 63 | 170 | 155 | 145 | 125 |
| 75 | 185 | 175 | 155 | 140 |
| 90 | 200 | 185 | 175 | 150 |
| 110 | 220 | 205 | 185 | 165 |
| 125 | 220 | 210 | 190 | 165 |
| 160 | 235 | 225 | 200 | 170 |
Name the class above the table, because the numbers move with it. The same manual’s PN16 table gives 65 cm at d 20 and 80 °C against the 70 cm above, and its PN10 table stops at 40 °C. A clause that says “PP-R” without a class has not said which table you used.
The expansion clause turns on one coefficient. Plain PP-R moves 0.15 mm per metre per kelvin, glass-fibre composite 0.035 and aluminium-layer 0.030, so a fibre-composite riser needs a different fixed-point layout. State the coefficient, the temperature difference you assumed, and where the fixed and sliding points land.
| Water temperature (°C) | Spacing at d 20 (cm) | Spacing at d 50 (cm) | Spacing at d 90 (cm) | Spacing at d 160 (cm) |
|---|---|---|---|---|
| 20 | 95 | 150 | 200 | 235 |
| 40 | 85 | 140 | 185 | 225 |
| 60 | 80 | 125 | 175 | 200 |
| 80 | 70 | 110 | 150 | 170 |
Pressure Testing: The Soak, the Main Test, and What the Test Cannot Prove
EN 806-4:2010, first edition, approved 22 March 2010 and still valid, is the European reference for testing a building water installation, and its section 6 is the clause to cite. The test pressure is 1.1 × the maximum allowable operating pressure, a minimum of 11 bar on the 10 bar maximum the standard sets for interior water mains. The main test runs 30 minutes with no detectable drop, only a gauge resolving 0.1 bar is acceptable, and where water and pipe differ by more than 10 K the system equalises first.

Thermoplastic pipe is the complication. It relaxes under pressure, so a gauge falls on a perfectly sound PP-R system, and section 6 therefore carries three lettered procedures with a table assigning them by material. Procedure A is for linear-elastic materials, meaning metals, for elastic materials such as PVC-U and PVC-C, for multilayer systems, and for combined metal-and-plastic systems up to DN/OD 63. Viscoelastic materials — PP, PE, PE-X, PA and PB, which is to say PP-R — take procedure B or C at every diameter and never procedure A. The DN/OD 63 line belongs to the combined-system rows, not the plastic ones.
Procedure B holds test pressure for 30 minutes, bleeds down to half the test pressure, and passes if the pressure then stays at or above that level for a further 30 minutes. Procedure C holds test pressure for 30 minutes and records it, records it again 30 minutes later and passes if the fall is under 0.6 bar, then watches a further two hours in which a fall of more than 0.2 bar indicates a leak. EN 806-4 is paywalled, so both readings come from a full-text reproduction of section 6, re-read on three passes, with the bleed-down and the 0.6 bar allowance each corroborated independently. Cite section 6 and the letter, never a sub-clause number you have not seen.
A maker’s own procedure may be specified instead. FV-Plast’s warranty-accepted route fills the line no earlier than 1 hour after the last weld by its Table 23, and 2 hours by the same manual’s text, so take the longer. It is then soaked filled at maximum operating pressure for 12 hours to 7 days, and only then taken to 1.5 × MOP — 15 bar on a 10 bar system — for 60 minutes, with a permitted drop of 0.2 bar. The soak lets the relaxation happen before the acceptance clock starts.
Two traps to close. The UK water-industry figure of 1.1 × (1.5 × maximum design pressure) belongs to service pipes and mains under the EN 805 family, not to a building installation. The second is where the letters come from: the water-regulations guidance notes that circulate as the easy source are not EN 806-4. Northumbrian Water’s guidance note captions its own figures “Test Procedure A. BS EN806.11.3.2” and “Test Procedure B. BS EN805.11.3.2”, attributing the second to the water-mains standard, and neither set of steps is the EN 806-4 procedure of that letter.
And a passed system test is not weld qualification. The clearest statement of that sits in the PE-HD companion part, not the PP one: DVS 2207-1 records in its explanatory section that “the quality evaluation of socket welding joints by the internal pressure creep test is only insufficiently possible” — in the 2005-09 edition, English translation 2007-08, since replaced by DVS 2207-1:2015-08. DVS 2207-11:2020-05 and SIMONA’s handbook carry no equivalent sentence, so take it for what it is: an observation about what an internal-pressure test can discriminate in a socket geometry, from the code for another material. Weld quality is controlled by the parameter clause and by competence, which is why section 2 names how an operator qualifies.
Before You Submit: Five Lines That Get a PP-R Method Statement Returned
Run the document against these five before it leaves your desk.
- A parameter table with no source. Name the rule and edition — DVS 2207-11:2020-05 — and whose published chart you reproduced.
- Times with no ambient condition. The figures are stated at 20 °C with moderate air movement; say what happens below +5 °C.
- A class with no ratio and no wall. PN20 is SDR 6 and 10.5 mm at DN63; a reviewer needs all three.
- A test pressure with no standard and no procedure letter. 1.1 × MOP under EN 806-4:2010 section 6, procedure B or C for PP-R, with the drop limit written out.
- A support table with no temperature. 170 cm at d 63 is a 20 °C figure; the same pipe at 80 °C takes 125 cm.
One more, which costs nothing: state in section 1 that the inspection and test plan is submitted separately, and reference its document number.
Conclusão
Work through the document in this order and it goes in once. Fix the class and the wall in section 4. Put the DVS 2207-11:2020-05 parameter table into section 6, with the tool temperature and the 20 °C ambient above it. Take the support spacing for that class at the design water temperature into section 7, and close section 8 with EN 806-4:2010 section 6, the procedure letter and its drop limit.
Keep the filled version as your standing template and the next project changes four numbers, not nine sections. If you need the class and wall data for section 4, ask before the submittal goes in.
Frequently Asked Questions
What is a PP-R pipe installation method statement?
It is the submittal describing how PP-R pipework will be installed and controlled, in enough detail that a second crew could repeat it. A reviewer approves a method, so every figure in it needs a named source and the condition under which it applies.
Which standard sets PP-R socket fusion times?
DVS 2207-11:2020-05 is the current technical rule for heated element welding of PP. Its recommended times are given at a heated-tool temperature of 260 ±10 °C and at 20 °C ambient with moderate air movement, and both conditions belong in the clause.
What test pressure does EN 806-4 require for a PP-R system?
Section 6 sets 1.1 × the maximum allowable operating pressure, a minimum of 11 bar on a 10 bar system, with a 30 minute main test. PP-R is viscoelastic, so under EN 806-4 section 6 it takes procedure B or C at every diameter and never procedure A; procedure C allows a fall of under 0.6 bar over the second 30 minutes and not more than 0.2 bar over the following two hours.
How far apart should PP-R pipe supports be?
It depends on diameter, pressure class and water temperature. For PN20 plain pipe on horizontal runs, FV-Plast’s Table 18c gives 95 cm at d 20 and 170 cm at d 63 at 20 °C, falling to 70 cm and 125 cm at 80 °C. Vertical runs take the horizontal figure × 1.3.
Can PP-R be fused below 5 °C?
Yes, provided the weld area is protected and the pipe wall is held at a workable temperature by prewarming, tenting or applied heat; welding may then proceed at any outdoor temperature. Watch the dew point, bring both parts to the same temperature, and make trial welds when conditions are in doubt.
Does a method statement include the inspection and test plan?
No. They are separate submittals: the method statement covers how the work is done and controlled, the ITP lists inspections, tests, hold points, who signs and against which record. Cross-reference the ITP document number in section 1 and keep the two apart.
Written by Justin, Technical & export team at IFAN ULTRA.
Reviewed 12 September 2026. Profile








